How to Specify a Package Substation for Your Project
What information is needed to specify a package substation?
The more project information you can provide at the start, the quicker the team can develop an accurate, compliant solution. However, you do not need to have every detail finalised before starting the conversation.
The most useful information includes:
- Required maximum demand or anticipated electrical load
- Incoming and outgoing supply voltage
- Required transformer rating (as determined by designers/ specifiers)
- DNO or IDNO area and technical specification
- Required LV outgoing ways and protection requirements
- Site footprint, access and delivery restrictions
- Whether the site is a new connection, upgrade, renewable-energy project or EV-charging development
- Future expansion requirements
If some details are still unknown, Jointing Tech can help identify the missing technical information and guide the specification process. You can also ask an expert or contact the technical team before committing to a design.
How do I select the right transformer rating?
The transformer rating must be based on the site’s current electrical demand, while allowing sensible capacity for future expansion. Choosing too small a transformer can limit the site’s ability to grow, while specifying unnecessary capacity can increase project cost and physical space requirements.
Jointing Tech can supply package substations with transformer ratings including:
- 315kVA
- 500kVA
- 800kVA
- 1000kVA
- 1500kVA
The correct choice depends on the anticipated load profile, diversity of demand, site type and the expected future electrical requirement. A commercial development, industrial facility, battery storage installation, or EV charging hub may have very different demand characteristics, even when the initial load appears similar.
It is also important to determine whether a single-ratio or dual-ratio transformer is needed. Multiple ratio options may provide extra flexibility if future network configurations or voltage requirements change.
Why do DNO and IDNO requirements matter?
A package substation must meet the technical requirements of the network operator responsible for the connection. This may be a Distribution Network Operator (DNO) or an Independent Distribution Network Operator (IDNO).
These requirements can affect the specification of:
- Transformer type and rating
- Ring Main Unit (RMU) configuration
- Protection and switching arrangements
- Low-voltage cabinet design
- Metering provisions
- Housing type and layout
- Earthing requirements
- Documentation and testing requirements
G81 compliance is particularly important for new electrical connections. G81 is a suite of documents that sets out technical standards for contestable electrical works, helping ensure installations meet the relevant network operator’s requirements.
By considering DNO or IDNO requirements at the start, you can reduce the risk of equipment changes, delayed approvals and unexpected costs later in the programme.
What RMU configuration do I need?
The RMU provides medium-voltage switching, isolation and protection within the package substation. The required configuration depends on the network arrangement, the type of connection and the protection requirements for the transformer.
For example, a simple radial supply may require a different arrangement than a development that requires an incoming and outgoing ring connection. The number and type of ways, switching function, protection function and metering requirements must all be considered.
Jointing Tech supplies RMUs from trusted manufacturers, which can be specified to meet major DNO requirements. Sharing the proposed network setup early in the process ensures the RMU is properly configured before procurement and assembly.
How should I specify the LV cabinet?
The LV cabinet distributes power from the transformer to the site’s outgoing circuits. It needs to match the site’s current demand, cable routes, outgoing feeder requirements and future expansion plans.
When specifying an LV cabinet, consider:
- The required current rating, such as 800A or 1600A
- The number of outgoing ways required
- The size and type of outgoing cables
- Whether air circuit breakers (ACBs) are required
- Metering or monitoring requirements
- Spare ways for future connections
- Site access for operation and maintenance
Jointing Tech can supply LV cabinets in configurations from 4-way to 7-way, helping you match the distribution arrangement to the project’s needs. Where possible, build expansion capacity into the initial design rather than relying on a later retrofit.
For associated project requirements, Jointing Tech can also supply specialist power cable and accessories alongside the substation package.
Which substation housing is right for the site?
The substation housing must provide suitable protection for the equipment while fitting the site layout, access arrangements and operator requirements.
GRP housings are a common choice for package substations because they are durable, lightweight compared with traditional construction methods and can be supplied as part of a complete engineered package. Available options include TR1, TR7 and TR18 housing styles, with additional ventilation where required.
When selecting a housing, consider:
- Transformer and switchgear dimensions
- Required ventilation
- Access for operation, maintenance and replacement
- Door configuration and security
- Location, appearance and planning requirements
- Delivery and installation access
- Future equipment expansion
Jointing Tech can also assist with projects involving brick-built substation enclosures with GRP doors and ventilation, including generator entry points when required.
Do I need a concrete base and GRP grating?
In most projects, the base and access arrangement should be considered as part of the overall package rather than separately at the end of the design process.
The precast concrete base is stable and durable, allowing for easy on-site installation. If included in the original package specification, it will help ensure that it fits the selected housing/equipment arrangement.
GRP grating can provide safe access around the substation and is especially useful in environments where corrosion resistance, drainage and long service life are important. By specifying the housing, base and grating together, you can reduce compatibility issues and avoid coordinating multiple suppliers.
Can cables and accessories be delivered with the substation?
Yes. Jointing Tech can combine the delivery of package substations with power cable accessories and related products, helping reduce site coordination and avoid separate deliveries.
This can include the cables and accessories needed for the wider connection or installation work, subject to the project specification. A combined supply approach can help simplify procurement, reduce storage requirements and ensure that key materials arrive in line with the installation programme.
If your programme is particularly tight, it is also worth checking substations currently in stock, which may be available for faster configuration and dispatch.
How quickly can a package substation be delivered?
Lead times depend on the selected equipment, technical specification, stock availability, required approvals and site readiness. However, Jointing Tech can deliver suitable package substations within two weeks from quotation to site for qualifying stock-based solutions.
Delivery planning should account for site access, vehicle requirements, lifting arrangements and the final positioning of the unit. Jointing Tech includes HIAB offloading within its package substation delivery service, helping reduce the need to arrange separate offloading equipment.
Engaging early gives the team more opportunity to identify stock-led options, align the build with the programme and ensure documentation is ready before delivery.
What testing and documents should I expect?
A fully specified package substation should be supplied with the relevant test certificates and technical documentation for the equipment and assembly. Documentation requirements can vary depending on the equipment, network operator and project scope.
Before placing an order, confirm the documents needed for your approval, installation and handover process. These may include:
- Equipment data sheets
- Test certificates
- Drawings and layout information
- Operating and maintenance information
- DNO or IDNO compliance documentation
- Manufacturer documentation
- Delivery and lifting information
Confirming this early helps avoid delays at the point of handover or energisation.
Get expert help with your specification
A successful package substation project starts with a clear technical brief, but you do not need to manage the process alone. Jointing Tech can help turn your load requirements, network information and site constraints into a complete package substation solution.
Whether you need help choosing a transformer rating, RMU arrangement, LV cabinet configuration, GRP housing or base design, the team can support your project from early specification through to delivery.
Contact Jointing Tech to discuss your package substation requirements, or visit the Package Substations hub to explore the complete range of solutions.